A broken crusher in Arizona has cost Capstone Copper about 5,000 tonnes of this year’s output. The setback lands as copper trades at its lowest since July.
MoneyTurkey Commodities Desk | 16 November 2026
Key points
- Capstone cut the bottom of its 2026 copper production guidance to 195,000 tonnes from 200,000 tonnes
- The primary crusher at Pinto Valley in Arizona is now due back in mid-December, with a partial restart on mobile crushers planned for mid-November
- London copper fell to its lowest level since 8 July on Monday
What happened
Capstone said in an operations update on Thursday, 12 November, that commissioning of Pinto Valley’s primary crusher showed several major mechanical components needed more work, and the parts are being made off-site by the original equipment maker. The crusher is now expected back in mid-December 2026, after plant operations had been due to resume in early November. The company expects the extra downtime to cut 2026 copper output by about 5,000 tonnes, depending on restart timing, and lowered the bottom of its consolidated guidance to 195,000 tonnes, Capstone and Mining Weekly reported.
In the meantime, temporary mobile crushers are expected to allow a partial restart of the concentrator in mid-November at up to 40,000 tonnes a day. Mining.com put that at about two-thirds of the 60,000-tonne-a-day capacity of the open-pit mine, about 130 km east of Phoenix.
A hard year gets harder
Capstone had already said in its 29 October results that it expected output at the bottom of its 200,000-to-230,000-tonne range, with costs at the upper end of guidance, Mining.com reported. Pinto Valley produced 6,358 tonnes of copper in the third quarter, down from 9,949 tonnes a year earlier, and group output fell 18% to 45,218 tonnes.
Investors took it badly. The shares fell 6.5% in Toronto on Thursday and another 4.5% to C$10.26 late on Friday morning, leaving the company worth about C$7.9 billion (US$5.6 billion), according to Mining.com. Jefferies analyst Tariq Fahad called the 5,000-tonne hit “modest” but said it “adds to a difficult operational year at Pinto Valley and Mantoverde”, and National Bank Financial’s Shane Nagle cut the stock to sector perform from outperform, citing “near-term operational uncertainty”.
Chile strike eases
Capstone also flagged a national truckers’ strike in Chile as a risk to shipments of concentrate and cathode and to deliveries of fuel and sulphuric acid, though its Mantoverde and Mantos Blancos mines had not been affected. Chile’s government reached a deal with the main trucking groups on the evening of 12 November to end the stoppage, including a 142-peso-a-litre diesel cut, Cooperativa reported, though some independent truckers kept protesting on Friday, according to Viajando Chile, citing La Tercera.
Copper under pressure
Three-month copper on the London Metal Exchange was down 0.9% at $13,273.50 a tonne at 07:00 GMT on Monday, a third straight daily fall, after touching its lowest level since 8 July, Reuters reported. Bloomberg linked the slide to a sell-off in technology shares and weaker Chinese economic data.
What to watch
- Whether Pinto Valley’s partial restart on mobile crushers starts on time this month
- Primary crusher recommissioning in mid-December
- Fourth-quarter output at Mantoverde and Mantos Blancos
Related on MoneyTurkey
For information only. Not investment advice.
Sources
- Capstone Copper: Capstone Copper Provides Update on Operations
- Mining.com: Capstone cuts copper outlook as restart slips
- Mining Weekly: Capstone advises of delay in Pinto Valley recommissioning
- Cooperativa: Gobierno logró desactivar el paro de los camioneros en su tercer día
- Viajando Chile: Chile’s truckers’ strike ends
- Reuters via Boursorama: Le cuivre à Londres au plus bas depuis plus de quatre mois
- Bloomberg via The Edge: Copper sinks to four-month low on tech rout, China growth woes